125th Street Subway Tunnel
On November 10, 2026, the 125th Street BID sent the MTA its formal comments on the Draft Scoping Document for the 125th Street Subway Tunnel. The BID supports a crosstown subway on 125th Street. Its comments ask the MTA to study, and protect, the businesses, residents and cultural institutions that will live through the construction.
21
requests to the MTA
62
pages of comments
47
exhibits of supporting evidence
The comments are 62 pages (PDF, 1 MB). Download the complete file with all 47 exhibits (PDF, 490 pages, 101 MB).

In brief
The MTA says the corridor is home to about 253,000 people and 82,000 jobs. The BID’s comments make the case that the people who have waited decades for this subway should not be the ones it displaces.
13–14 years
The MTA’s draft schedules only the tunnel. Counting Second Avenue Subway work already under way and the stations that must follow, the BID estimates 125th Street will host subway construction for about 13 to 14 years, with full service around 2040. It asks the MTA to publish its own estimate. p. 3
1 block
The block between Lenox Avenue and Adam Clayton Powell Jr. Boulevard, home to the Studio Museum in Harlem and the Urban League’s Urban Civil Rights Museum, would host Second Avenue Subway staging and then this project’s staging, ground improvement work and truck traffic. p. 2
32%
During the first phase of the Second Avenue Subway, 90% of surveyed businesses said construction hurt them, net sales fell 32% on average, and 98% got no financial support from the MTA. p. 3
30 million+
The BID’s ten pedestrian counters record more than 30 million passes a year. The draft’s study of businesses looks for buildings removed and residents added, not customers lost. A scope that does not measure the harm will not produce findings that reduce it. p. 2
Harlem’s merchants, property owners, residents and cultural and community organizations stand to gain from that service, but only if they survive its construction.
125th Street BID comments, Part I, p. 2
Local businesses are being asked to put up with years of disruption to build a tunnel that brings no station, no new riders and no new foot traffic until a later phase. Unlike Second Avenue’s neighborhood retail, 125th Street is a regional shopping destination with a dense concentration of nationally known cultural institutions, so the BID asks the MTA to tailor its protections to the corridor it is building under. p. 8
The requests
The BID asked that the final scope respond to each request by number, and explain why for any it declines. Each link opens the request in the comments.
Part VII
The BID proposes that the MTA make this program a condition of approval and put its terms in a written agreement with the BID before construction begins. Each piece has a precedent in the MTA’s own practice or lessons. Read Part VII, p. 49
Business access standards
Continuous pedestrian access to every door, a minimum clear sidewalk, protected delivery windows and a holiday-season moratorium on new closures.
Visibility and signage
See-through fence panels, business signage and custom fence wraps at every work site from day one.
A construction liaison
A named MTA liaison for 125th Street, a 24-hour hotline and monthly three-month look-ahead schedules.
Marketing and wayfinding
A corridor campaign developed with the BID and launched when work begins, not after sales fall.
A business support fund
Grants and technical assistance, funded as a project cost and run with the BID.
Local procurement
Priority for buying goods and services from corridor businesses during construction.
Building protection
Condition surveys before work starts, real-time vibration monitoring and a fast claims process.
Relocation assistance
No less than federal Uniform Relocation Act levels for anyone displaced, whatever the funding source.
Permanent structure design
Setbacks, landscaping, street-level retail and public space at every vent building and kiosk.
Clean construction
Tier 4 or electric equipment, enclosed slurry and spoil handling, dust controls and public air monitoring.
An advisory committee
Monthly meetings with the BID and community boards from the start of work through restoration.
Corridor upkeep and cultural protection
Rodent control, daily cleaning and lighting at work sites; Harlem Holiday Lights, banners, wayfinding and murals protected.
Read the part that matters to you
The comments are long because the BID backed every point with evidence. Start with the sections written for you. Each link opens the comments at that page.
If you run a shop, restaurant, salon or office on the corridor
If you own a building on or near 125th Street
If you run a theater, museum, gallery or arts program
If you live, work or get around on the corridor
New to the project? Start with the summary of the BID’s position and what the MTA’s draft proposes, or read about the tunnel project.
The full document
Every source the comments cite is attached as a numbered exhibit. Each exhibit below is its own PDF, so you can open just the one you need.
PDF · 62 pages · 1 MB
The BID’s comments
The comment letter by itself, Parts I to IX and the exhibit index.
PDF · 490 pages · 101 MB
Complete file with all 47 exhibits
The comments and every exhibit in one file, as sent to the MTA. A large download.
PDF · October 2026
The MTA’s Draft Scoping Document
The document the BID’s comments respond to.
What happens next